What document establishes the amount to be paid for each portion of the work as the project progresses?
Click or press Space to flip
B.Schedule of values
A Schedule of Values breaks down the contract sum into portions of work, used as the basis for progress payments.
All options: A) Change order · B) Schedule of values · C) Purchase order · D) Work order